Example of the Floor Mounting and laying
 
  1.Floor installment
  1.1The survey building area, confirms and the blueprint match case, if does not tally, then do not construct, and immediately discussed with the owner or construction business, explained does not tally place.
  1.2Confirmed floor all regions change highly, laying down of in order to help the floor.Available construction horizon, altazimuth or laser horizon test.Simultaneously confirms the existing fixed structure like pillar, the threshold and so on quantity, the position and the ground to the top high change.The elevator or the floor must coordinate characteristic of the certain region, decided the special method, guaranteed installment the floor and the base, enable the floor to have the correct suitable horizontal plane.Cannot cause when the field condition the floor level installment also cannot coordinate all structure request, do not have rashly to construct, after in order to avoid constructs affects the project quality.
  1.3Establishes the initial station, according to the altazimuth test result, uses the black marking line to delimit two vertical base directrixes again, decided the floor lays down the reference.Nearby receiving the position, must cut the floor not to have to be smaller than the 30cm width, in addition along vertical grounding according to 600x 1200mm distribution base.
  1.4With the laser horizon is the datum, calibrates the base level, guarantees in three meters scopes, it completes the highly horizontal error not to have to surmount ±1.5mm, also the entire level floor does not have to surmount ±2.5mm.
  1.5The use fire protection glue water fixed base, permits 12 hour coagulation times, forbids the staff in already on the floor which completes the work, guarantees the construction quality.
  1.6Installs the specific crossbeam, starts from the initial station, is attached to the crossbeam peak of the horizontal base, again uses the special components to be fixed, confirmed each crossbeam has arranged suitably.Guaranteed the floor and the base maintain the correct arrangement, also all floors can level, the level.
  1.7Installs the impractical floor, along the bottom stitch binding four floors, again confirmed the floor and the base and the kneading board are vertical to the agent.If not vertical, must adjust first, but otherwise will be able to cause the arrangement out of control to have to make a fresh start.This time has any uneven floor, must correct.
  2.Cuts the peripheral floor
  2.1In installs floor period side, available receives the base support side cutting floor.
  2.2Side each kind receives the floor when the floor and the wall, the pillar or other end surface place cutting, the floor must survey first, enables the floor which cuts to conform to also the close union outside the wall surface the profile.The wall surface and cuts between the floor gap must in positive and negative 1.5mm, the floor need irregular cutting to coordinate time the pillar or the circular pipe.Must the precision measuring, guarantee the floor and the garden cambered surface coordination.At the same time, confirmed all cutting floor all must fixed (for example have need with the base to be possible multipurpose extra base) also the maintenance horizontal, smooth and the arrangement is neat.
  3.Installs the appendix
  3.1All snow wild goose original factory floor appendix manufacture and the supply all conforms to design the snow wild goose floor series, if appendix of the non-snow wild goose manufacture must be accommodating with the snow wild goose floor system, then this appendix should conform to the snow wild goose related design standard and the standard.
  3.2Pitch stair
  The most common impractical floor appendix is the pitch, the stair, will be able to have very many human of or the machinery uses these pitches, the stair takes the channel.Therefore all pitch stair must use the high quality the material and the high grade construction technology.The snow wild goose provides the all appendix detailed blueprint, and explained the assembly law, the constructor must be familiar with also according to all blueprint assembly.Pitch of, the stair the all floor all must and the support vertical, and with floor and first floor grounds around a house maintenance level; When installs all snow wild goose floor, the constructor must keep firmly in mind the user the safety is the construction first essential factor.
  3.3The floor opens the hole
  The floor can open the hole differently because of many reasons, the company to opens the hole method to be able to match by different decoration processing.Opens the hole to have the structure integrity, the outward appearance neat, not sharp-cornered or the burr in order to avoid injures the personnel; Every cutting part must use the EVA fire protection to become spongy protects the material.Uses for in the floor hole to make the air vent in the situation, must consider the addition adjustment employing according to ability air may adjust.
  3.4Excision
  (1)Certainly must process the floor carefully cutting place, confirmed cutting place does not have the acute angle or the burr, in order to avoid personnel in work time because of treads cutting place to be injured.
  (2)Side all receives cuts place or cuts the hole place, should buckles fixed by the bond or the machinery.
  (3)The metal buckles not to permit the exposition or to protrude in the floor walks above the surface.
 
[Print]    [Back]   