Guide to Floor Laying
 
The permanence guards against the static electricity PVC floor construction plan
Construction schedule:
Sweeps clear the ground - > the shop earth to lead the electrical network - > to draw out the grounding - > to spread leads the bakelite - > the shop to paste the floor - > to open V die - > to lay down the welding rod - > the thermit welding to repair and maintain - > the surface cleanly - > to examine the performance.
The floor installs the structure drawing:
Construction standard:
1. This standard is suitable in the polyvinyl chloride is a main body.Matches the conducting material and so on to help the medicinal preparation, after the plasticization, the mould pressing processing becomes guards against the static electricity half rigid polyvinyl chloride massive plastic floor, mainly uses in requesting to guard against the static electricity, to lead the static electricity the ground construction.
2. To the ground request ground request smooth, dry (cement floor surface should turn white) not obviously uneven, does not get up the sand, does not peel off the shell, the surface irregularity should be smaller than 2/1000mm, may be the terrazzo floor, the ceramic tile ground or the cement floor and so on.
3. Job practice
  3.1 Cleans up the ground, seeks the middle line.
First floats the ground the ash elimination to be clean, then discovers the room with the measuring instrument the central position, draws the central hairline, the request hairline vertical division.
  3.2 Lays down the copper foil network to spread little in the copper foil leads the bakelite, starts the neighboring shop from the central position in the ground.
  3.3 Spreads cementing agent evenly in the ground, treats does.
  3.4 Waits in the situation which the ground cementing agent touches resembles dry must sticks to start to lay down the floor.Nearby the floor strikes with the rubber hammer, guaranteed the caking between the floor is reliable, until the entire room construction finished.
  3.5 The floor puts together the seam place to open V die with the key seating machine, then lays down the welding rod in the slot place, puts together the seam place with the plastic welding torch in the floor to carry on the welding rod models hotly the welding, and outdoes with the shaving knife the floor the welding rod to shear evenly.
  3.6 After the board lays down, the surface must clean up cleanly.
4、Construction quality requirement
  4.1 Static electricity PVC floor resistance104-109Ω。
  4.2The surface does not have the steam bubble, not peels off the shell the phenomenon.
  4.3Not obvious construction pollution.
5、Routine maintenance maintenance
  5.1Lays aside the heavy item when the floor, should avoid the heavy item towing on the floor scratches, its contact face is not suitable too slightly, when necessity available log liner.
  5.2Panel walks or the work when the place, cannot dress has the metal nail shoe, cannot use sharp, hard to delimit on the floor surface scratches and the rap.
  5.3When clean with pushes the dry moist swab to tow, solvents and so on dirty place available liquid detergent carry on the clean.
 PVCThe floor installs the graphical representation
 Copper foil
 Welding rod
 Construction schedule
 Sweeps clear the ground -> shop earth to lead the electrical network -> to draw out the grounding -> to spread the force rubber -> to spread leads the bakelite -> shop to paste the floor -> to weld the floor seam -> surface clean -> examination performance
 
 
[Print]    [Back]   